NAACP Sues xAI for Operating Unpermitted Gas Turbines in Mississippi
The NAACP filed a lawsuit against Elon Musk's xAI in U.S. District Court for the Northern District of Mississippi, accusing the company of Clean Air Act violations from emissions at its Southaven power plant. The suit seeks to halt operations of unpermitted turbines powering data centers in Memphis, Tennessee. xAI did not immediately respond to a request for comment.
NASA's Earth Observatory / Wikimedia (CC BY 2.0)S. District Court for the Northern District of Mississippi. The lawsuit accuses xAI of violating the Clean Air Act due to emissions from its makeshift power plant in Southaven, Mississippi. The NAACP is represented by the Southern Environmental Law Center and Earthjustice in the lawsuit.
xAI has been using dozens of methane gas generators without permits in Southaven, Mississippi. The power plant in Southaven powers xAI's data centers in south Memphis, Tennessee. xAI and its subsidiary MZX Tech, LLC installed and operated 27 gas turbines in Southaven, Mississippi, between August and December 2025.
The 27 gas turbines emit smog-forming pollutants and particulate matter. The NAACP seeks to force xAI to stop operating its unpermitted turbines in Southaven, Mississippi. The NAACP seeks declaratory and injunctive relief to require xAI to cease operating the Colossus Gas Plant until obtaining required permits.
Relief Sought Includes Pollution Controls and Penalties The NAACP seeks to require xAI to apply necessary pollution controls.
The NAACP seeks civil penalties from xAI for each day of violation. xAI has been using natural gas-burning turbines for months at its facility in Southaven, Mississippi. xAI operates the Colossus 1 and Colossus 2 data centers in Memphis, Tennessee.
The Colossus 1 and Colossus 2 data centers are located just across the Mississippi state line from Southaven. Tens of thousands of people live, work, and study near xAI's power plant in Southaven, Mississippi. Hundreds of thousands of people live in greater Memphis.
xAI's Expansion Plans and Regulatory Actions xAI is planning to build a data center named Macrohardrr in Southaven, Mississippi.
xAI is building a permanent power plant in Southaven, Mississippi, that will use 41 natural gas-burning turbines. Mississippi state regulators granted a permit to xAI in March to build a power plant in Southaven with 41 permanent turbines. The NAACP wants Mississippi state regulators to revoke the permit granted to xAI in March.
xAI's Colossus 1 and 2 data centers and power plant in Southaven have faced protests for more than a year. Gas turbines are visible at an xAI data center on Riverport Rd in Memphis, Tennessee, on April 25, 2025. SpaceX acquired xAI in February.
25 trillion. xAI did not immediately respond to a request for comment.
Story Timeline
6 events- 2026-04-15
NAACP files lawsuit against xAI in U.S. District Court for the Northern District of Mississippi.
1 sourceunattributed - March 2026
Mississippi state regulators grant permit to xAI for power plant with 41 permanent turbines in Southaven.
1 sourceunattributed - February 2026
SpaceX acquires xAI, valuing the combined entity at $1.25 trillion.
1 sourceunattributed - August-December 2025
xAI and MZX Tech, LLC install and operate 27 gas turbines in Southaven, Mississippi.
1 sourceunattributed - April 25, 2025
Gas turbines visible at xAI data center on Riverport Rd in Memphis, Tennessee.
1 sourceBrandon Dill | The Washington Post | Get - Since early 2025
xAI's Colossus 1 and 2 data centers and Southaven power plant face protests for more than a year.
1 sourceunattributed
Potential Impact
- 01
Ongoing protests and legal scrutiny on xAI facilities, impacting community relations in greater Memphis area.
- 02
Civil penalties for each day of violation, increasing financial costs for xAI's temporary power setup.
- 03
Potential halt to unpermitted turbine operations in Southaven, affecting power supply to Colossus 1 and 2 data centers.
- 04
Requirement for xAI to install pollution controls, reducing emissions of smog-forming pollutants near tens of thousands of residents.
- 05
Possible revocation of March permit for 41 permanent turbines, delaying xAI's Macrohardrr data center plans.
Transparency Panel
Related Stories
GB NewsTrump Announces Plans to Replace Fed Chair Powell and Review UK Trade Deal
President Donald Trump threatened to fire Federal Reserve Chair Jerome H. Powell if he does not resign soon. Trump also warned of changes to the UK-US Economic Prosperity Deal due to Britain's stance on the Iran war. The Strait of Hormuz remains contested with a U.S. naval blocka…
cnbc.comTrump Says He Will Fire Fed Chair Powell If Term Extended
President Donald Trump said he would fire Federal Reserve Chair Jerome Powell if Powell does not leave the central bank after his successor is confirmed. Trump also stated that an investigation into the renovation of the Fed's headquarters must continue. Powell's term as chair ex…
US Treasury Announces Continued Efforts Against Iran's Illicit Networks and Record Tax Refunds
The US Treasury stated it will continue actions to dismantle Iran's illicit smuggling and terror proxy networks. Treasury officials also confirmed a record tax refund season this year, attributing it to tax cuts for working families. The announcements come amid mentions of high g…